A development team member learned that one of the product features delivered in the last sprint would have greater business value if a small enhancement was made to the feature. What should the project manager do next?

QuestionsCategory: PMPA development team member learned that one of the product features delivered in the last sprint would have greater business value if a small enhancement was made to the feature. What should the project manager do next?
Admin Staff asked 1 year ago
A development team member learned that one of the product features delivered in the last sprint would have greater business value if a small enhancement was made to the feature.
What should the project manager do next?

A. Conduct another sprint planning meeting and add the necessary story.

B. Discuss this feature in the next sprint planning meeting.

C. Discuss this feature during the upcoming retrospective meeting.

D. Advise the team member to better prepare before sprint planning.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.