A distributed protect team wants to use the common ground principle to ensure that they have a common understanding of the scope. The team asks the protect lead to set up a workshop. What should the project lead do? A. Ask the senior members of the development team to elaborate on the scope in detail B. Invite participants to the workshop with su cient lead time to prepare C. Reduce the number of participants to ensure that consensus is reached easier D. Provide the participants with specific instructions and sot the expectations Correct Answer: B This question is in PMP exam For getting PMP Certificate