A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully. What should the project manager do? A. Invite the Scrum team members as optional participants. B. Ask the Scrum team members to share retrospectives. C. Invite the Scrum team members as mandatory participants. D. Ask the scrum master to attend the workshops. Correct Answer: C This question is in PMP exam For getting PMP Certificate