A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team’s efforts. What should the project manager do in this situation?

QuestionsCategory: PMPA key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team’s efforts. What should the project manager do in this situation?
Admin Staff asked 1 year ago
A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts.
What should the project manager do in this situation?

A. Work to understand the key stakeholder's concerns and provide feedback in regular project status reports

B. Arrange an ad hoc meeting to address the key stakeholder's concerns with team members

C. Reinforce with the key stakeholder that the project is performing on schedule

D. Escalate the situation to the project sponsor because the key stakeholder's behavior is impacting progress










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.