A key team member informs the project manager that they have been accepted to a master’s degree program. The team member explains that the first semester of the master’s program will coincide with the last phase of the project. What should the project manager do?

QuestionsCategory: PMPA key team member informs the project manager that they have been accepted to a master’s degree program. The team member explains that the first semester of the master’s program will coincide with the last phase of the project. What should the project manager do?
Admin Staff asked 1 year ago
A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master's program will coincide with the last phase of the project.
What should the project manager do?

A. Suggest the team member postpone their enrollment in the master's program until the project is completed

B. Assess the team member's commitment to the master's program and its impact on project performance

C. Ask the team member to delegate some of their tasks to another colleague during the last phase of the project

D. Ask the team member to inform human resources (HR) about their enrollment in the master's program










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.