A local bank has all of its infrastructure in the cloud. An update was applied to the main database server at 5:00 a.m. on Monday morning, and the database was then corrupted and unusable. It had to be restored from backup. The last backup was taken the night before at 10:00 p.m. The database was then restored successfully, but seven hours' worth of data was lost, which is deemed unacceptable. Which of the following needs to be updated in the DR plan? A. Recovery point objective B. Statement of work C. Service-level agreement D. Recovery time objective  Suggested Answer: A Community Answer: A This question is in CV0-003 CompTIA Cloud+ Exam For getting CompTIA Cloud+ Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by CompTIA. Trademarks, certification & product names are used for reference only and belong to CompTIA. The website does not contain actual questions and answers from CompTIA's Certification Exams.