A major public-transportation construction project is aimed at significantly reducing emissions. The project has been severely delayed due to noncompliance with environmental codes and bylaws. What should the project manager have done to prevent this?

QuestionsCategory: PMPA major public-transportation construction project is aimed at significantly reducing emissions. The project has been severely delayed due to noncompliance with environmental codes and bylaws. What should the project manager have done to prevent this?
Admin Staff asked 1 year ago
A major public-transportation construction project is aimed at significantly reducing emissions. The project has been severely delayed due to noncompliance with environmental codes and bylaws.
What should the project manager have done to prevent this?

A. Appointed a senior environmental compliance officer to report directly to the project manager.

B. Approached the regulator for a partial waiver in light of the environmental importance of the project.

C. Incorporated su cient schedule reserves based on similar delays in past projects.

D. Mapped environmental compliance requirements, identified risks to achieving them, and prepared mitigations.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.