A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member’s performance was poor, and the team had difficulty meeting the iteration goals. How should the project manager handle this situation?

QuestionsCategory: PMPA member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member’s performance was poor, and the team had difficulty meeting the iteration goals. How should the project manager handle this situation?
Admin Staff asked 1 year ago
A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the team had difficulty meeting the iteration goals.
How should the project manager handle this situation?

A. Speak to the team member regarding the need to improve performance.

B. Allow the project team to discuss the problem with this team member.

C. Discuss the issue with the team member's functional manager.

D. Inform the human resource (HR) department about the issue.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.