A network engineer must design a Cisco HyperFlex solution based on these requirements: • two clusters in the main data center consisting of five HyperFlex nodes • one edge node for the remote branch • cluster nodes that use one rack unit of space Which two devices should be used in the remote branch cluster for this design? (Choose two.) A. UCS B200 B. Gigabit Ethernet Switch C. Fabric Interconnect 6300 D. HX240c E. HX220c Suggested Answer: AD This question is in 300-610 Designing Cisco Data Center Infrastructure (DCID) Exam For getting Cisco Certified Network Professional Data Center (CCNP Data Center) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by Cisco. Trademarks, certification & product names are used for reference only and belong to Cisco. The website does not contain actual questions and answers from Cisco's Certification Exam.