A new project manager is working on a time-sensitive social media strategy for a software development company that is building a communications management plan for the stakeholders. This is the first major project since the company shifted to working remotely on a full- time basis. After reviewing all previous company artifacts, the project manager finds a standard operating procedure (SOP) document outlining how all communication should take place. How should the project manager proceed? A. Adhere to the SOP for the project, make a note of required changes, and escalate to the change management board. B. Use the SOP as a base plan and make updates during the control and monitoring phase of the project. C. Ignore the SOP and write a separate communications management plan for this project. D. Assess the SOP for relevancy, make updates, and circulate to the stakeholders for comment during project planning. Correct Answer: D This question is in PMP exam For getting PMP Certificate