A new risk practitioner finds that decisions for implementing risk response plans are not being made. Which of the following would MOST likely explain this situation? A. The organization's risk awareness program is ineffective. B. The organization has a high level of risk appetite. C. Risk ownership is not being assigned properly. D. Risk management procedures are outdated. Â Suggested Answer: C This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.
Please login or Register to submit your answer