A plan for managing the end of a supplier contract should be created when? A. The contract is being negotiated B. The contract is about to be ended C. The Supplier Manager decides that there is a risk the contract might need to end soon D. The contract has been agreed Correct Answer: A This question is in ITIL Foundation exam For getting ITIL Foundation Certificate