A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer. What conclusion should the project manager come to with regard to the product owner's statement? A. The product owner trusts the team and is marking the product as complete. B. The product owner does not have visibility into what the team has done in the product increment. C. The product owner will release the product to customers without showing them a demo. D. The product owner has evaluated the product against the definition of done (DoD). Correct Answer: D This question is in PMP exam For getting PMP Certificate