A product owner is trying to understand how many of the user stones have been completed within a 2-week sprint. How should the project manager approach this situation? A. Use retrospectives to deliver the nished products. B. Invite the product owner to regular standup meetings. C. Have a face-to-face conversation with the product owner. D. Share the burndown chart with the product owner. Correct Answer: D This question is in PMP exam For getting PMP Certificate