A project delivers every 2 weeks. The customer raises a complaint because they do not perceive business value in the products delivered even though deliveries have been completed in a timely manner. Which activity should the project manager undertake? A. Change the delivery project approach. B. Review the risk analysis. C. Perform a cost-benefit analysis. D. Review the definition for the minimum viable product (MVP). Correct Answer: D This question is in PMP exam For getting PMP Certificate
Please login or Register to submit your answer