A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate. What should the project manager do next? A. Hire a company in country B to perform a quality check before shipment B. Evaluate the procurement contract to determine the agreed-upon specifications C. Escalate the issue to the purchasing department for review D. Add an additional task to cut the received part according to the specifications B Correct Answer: B This question is in PMP exam For getting PMP Certificate