A project for a new product launch is in a very initial stage and the requirements are evolving. Due to stiff competition in the market, the customer would like to launch the product keeping the scope exible. The project team intends to start the work based on the forecast of a similar project delivered last year. Which project approach suits the scenario? A. Execute it as a Scrum project B. Execute it as a predictive project C. Execute it using the same approach as the reference project D. Execute it as a project with stage gates Correct Answer: A This question is in PMP exam For getting PMP Certificate