A project has completed the first phase. During the lessons learned meeting, the project manager reported that the project was successful because it was on time, on budget, and on scope. The sponsor objected and said that other project benefits, such as cost reduction of the product and system response time, were not achieved. What may have caused this situation?

QuestionsCategory: PMPA project has completed the first phase. During the lessons learned meeting, the project manager reported that the project was successful because it was on time, on budget, and on scope. The sponsor objected and said that other project benefits, such as cost reduction of the product and system response time, were not achieved. What may have caused this situation?
Admin Staff asked 1 year ago
A project has completed the first phase. During the lessons learned meeting, the project manager reported that the project was successful because it was on time, on budget, and on scope. The sponsor objected and said that other project benefits, such as cost reduction of the product and system response time, were not achieved.
What may have caused this situation?

A. The change control plan was not followed by the project manager.

B. The acceptance criteria were not accurately defined.

C. The items did not appear in the project management plan.

D. The benefits should have been managed at the organizational level.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.