A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product. What should the project manager do?

QuestionsCategory: PMPA project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product. What should the project manager do?
Admin Staff asked 1 year ago
A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product.
What should the project manager do?

A. Use the remaining time and resources to add additional scope to the project without spending the project budget.

B. Ensure product quality by spending the remaining resources and time on additional quality checks for the product.

C. Acknowledge the project closure criteria has been met and release the remaining budget and resources.

D. Obtain approval from the sponsor to add additional functionality to the project deliverables with the leftover budget.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.