A project has progressed significantly and is getting close to completion. The project manager observed that team members are no longer focused and have started arriving to work late. What should the project manager do?

QuestionsCategory: PMPA project has progressed significantly and is getting close to completion. The project manager observed that team members are no longer focused and have started arriving to work late. What should the project manager do?
Admin Staff asked 1 year ago
A project has progressed significantly and is getting close to completion. The project manager observed that team members are no longer focused and have started arriving to work late.
What should the project manager do?

A. Engage functional managers to secure roles for team members.

B. Hold motivation sessions to keep team member morale high.

C. Ask for replacement project team members.

D. Penalize team members who arrive to work late.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.