A project is 70% complete when the project sponsor requests an additional deliverable. What should the project manager do first?

QuestionsCategory: PMPA project is 70% complete when the project sponsor requests an additional deliverable. What should the project manager do first?
Admin Staff asked 1 year ago
A project is 70% complete when the project sponsor requests an additional deliverable.
What should the project manager do first?

A. Negotiate with the project sponsor on the possible alternatives

B. Determine the possible impact of this change on all aspects of the project

C. Reject the request as being too late and leading to major scope creep

D. Submit the request to the change control board (CCB) for a decision










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.