A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery noti ed the project manager that there is a capacity issue for the team doing the installation. What should the project manager have done to prevent this situation from happening?

QuestionsCategory: PMPA project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery noti ed the project manager that there is a capacity issue for the team doing the installation. What should the project manager have done to prevent this situation from happening?
Admin Staff asked 1 year ago
A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery noti ed the project manager that there is a capacity issue for the team doing the installation. What should the project manager have done to prevent this situation from happening?

A. defined the skill requirements more clearly in the scope statement.

B. Asked the manager to follow the agreed-upon resource management plan.

C. Conducted periodic reviews with the manager on resource availability.

D. Consulted with the installation team on a regular basis to check for con icts.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.