A project is ending its fth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration. What should the project lead do?

QuestionsCategory: PMPA project is ending its fth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration. What should the project lead do?
Admin Staff asked 1 year ago
A project is ending its fth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.
What should the project lead do?

A. Register an issue and escalate it to the project sponsor.

B. Invite the stakeholders to discuss a new prioritization.

C. Estimate the impact and consult with the product owner.

D. Increase the team capacity to nish the project on time.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.