A project is ending its fth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration. What should the project lead do? A. Register an issue and escalate it to the project sponsor. B. Invite the stakeholders to discuss a new prioritization. C. Estimate the impact and consult with the product owner. D. Increase the team capacity to nish the project on time. Correct Answer: C This question is in PMP exam For getting PMP Certificate