A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do? A. Complete the sprint and seek a waiver from the regulator. B. Perform a sprint risk assessment and analyze challenges. C. Add more items to the sprint backlog that will add value. D. Complete the sprint, but do not release the deliverable. Correct Answer: B This question is in PMP exam For getting PMP Certificate