A project manager accepts a delivery at the project site but the items are of a poor quality. The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected. What should the project manager do going forward?

QuestionsCategory: PMPA project manager accepts a delivery at the project site but the items are of a poor quality. The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected. What should the project manager do going forward?
Admin Staff asked 1 year ago
A project manager accepts a delivery at the project site but the items are of a poor quality. The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected.
What should the project manager do going forward?

A. Allocate extra time to inspect deliveries for quality assurance upon arrival at the site

B. Review the contract requirements and ask for the applicable evidence for quality assurance

C. Have the vendor issue the quality documentation prior to the next delivery

D. Call the vendor and have them verbally guarantee the quality of the next site delivery










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.