A project manager analyzes the cumulative flow chart and identifies a bottleneck in the testing activities from a self-organizing team. After discussing it with the team, a gap related to testing skills is identified. What should the project manager do to address the issue?

QuestionsCategory: PMPA project manager analyzes the cumulative flow chart and identifies a bottleneck in the testing activities from a self-organizing team. After discussing it with the team, a gap related to testing skills is identified. What should the project manager do to address the issue?
Admin Staff asked 1 year ago
A project manager analyzes the cumulative flow chart and identifies a bottleneck in the testing activities from a self-organizing team. After discussing it with the team, a gap related to testing skills is identified.
What should the project manager do to address the issue?

A. Support the team to identify an approach to resolve the problem.

B. Ask the development team to slow down so the testers can catch up.

C. Provide training to the entire team so they all will be able to perform tests.

D. Onboard a new project team member who has testing skills.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.