A project manager encounters a governance issue during the project execution phase. One of the team members complains about receiving assignments from multiple people and states they are not able to work effectively. What should the project manager establish first in the project governance structure? A. Clear project work breakdown structure (WBS) and timeline B. Resource management and con ict resolution plan C. Risk management and issues resolution plan D. Clear responsible, accountable, consult, and inform (RACI) matrix Correct Answer: D This question is in PMP exam For getting PMP Certificate