A project manager has been asked for performance feedback regarding one of the team members. The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance. What should the project manager do next? A. Identify levels of decision-making authority B. Evaluate demonstrated task accountability C. Determine the appropriate approach D. Analyze team member in uence Correct Answer: C This question is in PMP exam For getting PMP Certificate