A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case. What should the project manager do? A. Ensure the client representative is involved in the estimation. B. Ensure that a 20% contingency is included in the estimation. C. Review the completion costs of similar projects. D. Review the lessons learned from similar projects. Correct Answer: C This question is in PMP exam For getting PMP Certificate