A project manager has been assigned to a project and receives the project charter from the project management office (PMO). The document is very clear about customer requests. During Project Scope Management some requirements seem to be different from the ones speci ed within the project charter. What should the project manager do?

QuestionsCategory: PMPA project manager has been assigned to a project and receives the project charter from the project management office (PMO). The document is very clear about customer requests. During Project Scope Management some requirements seem to be different from the ones speci ed within the project charter. What should the project manager do?
Admin Staff asked 1 year ago
A project manager has been assigned to a project and receives the project charter from the project management office (PMO). The document is very clear about customer requests. During Project Scope Management some requirements seem to be different from the ones speci ed within the project charter.
What should the project manager do?

A. Modify the baseline of the project for minor impact changes to the project scope

B. Use a focus group and brainstorming sessions to gather more details about the project scope

C. Register the changes in the configuration management plan and send it to the change control board (CCB)

D. Explain to the sponsor that these requests could endanger the schedule and cost of the project










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.