A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the year. The project team is concerned that one of those tickets could be the winner. What should the project manager do first?

QuestionsCategory: PMPA project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the year. The project team is concerned that one of those tickets could be the winner. What should the project manager do first?
Admin Staff asked 10 months ago
A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the system caused
10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the year. The project team is concerned that one of those tickets could be the winner.
What should the project manager do first?

A. Reassure the sponsor by explaining the probability of this risk materializing is extremely low.

B. Carry out tests to verify that the system does not fail again due to the high occurrence of events.

C. Review the list of risks to verify that this issue was considered and execute the detailed action plan.

D. Inform the sponsor about the issue and make a request for su cient funds to be made available.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.