A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing. What should the project manager do to create a positive environment? A. Help the teams in establishing and adhering to their ground rules and revisit after regular intervals B. Copy the ground rules established by another project and provide them to the teams C. Establish the team ground rules and share them with the team for strict adherence D. Extract the organization's policies and processes, customize them, and give them to the teams to adhere to Correct Answer: A This question is in PMP exam For getting PMP Certificate