A project manager has been assigned to run an organization’s first agile project. The project team has no previous agile experience. A high-level scope has been defined, but the team is not clear as to what to work on first. What should the project manager do to address this situation?

QuestionsCategory: PMPA project manager has been assigned to run an organization’s first agile project. The project team has no previous agile experience. A high-level scope has been defined, but the team is not clear as to what to work on first. What should the project manager do to address this situation?
Admin Staff asked 1 year ago
A project manager has been assigned to run an organization's first agile project. The project team has no previous agile experience. A high-level scope has been defined, but the team is not clear as to what to work on first.
What should the project manager do to address this situation?

A. Hire an external consultancy service to help define the project scope.

B. Work with the product owner to define the initial product backlog.

C. Keep the project on hold until a detailed scope document is defined.

D. Dedicate the first three sprints with the team to define the sprint backlog.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.