A project manager has been assigned to run an organization's first agile project. The project team has no previous agile experience. A high-level scope has been defined, but the team is not clear as to what to work on first. What should the project manager do to address this situation? A. Hire an external consultancy service to help define the project scope. B. Work with the product owner to define the initial product backlog. C. Keep the project on hold until a detailed scope document is defined. D. Dedicate the first three sprints with the team to define the sprint backlog. Correct Answer: B This question is in PMP exam For getting PMP Certificate