A project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the importance of the project meeting the company’s strategy, investment, and compliance requirements. What should the project manager do?

QuestionsCategory: PMPA project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the importance of the project meeting the company’s strategy, investment, and compliance requirements. What should the project manager do?
Admin Staff asked 10 months ago
A project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the importance of the project meeting the company's strategy, investment, and compliance requirements.
What should the project manager do?

A. Put into place a project governance model in line with the requirements

B. Replicate the organizational governance to the project governance

C. Create an organizational project management governance

D. Ask the organization to create a project portfolio governance










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.