A project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the importance of the project meeting the company's strategy, investment, and compliance requirements. What should the project manager do? A. Put into place a project governance model in line with the requirements B. Replicate the organizational governance to the project governance C. Create an organizational project management governance D. Ask the organization to create a project portfolio governance Correct Answer: A This question is in PMP exam For getting PMP Certificate