A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources What strategy should the project manager implement to deal with this situation?

QuestionsCategory: PMPA project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources What strategy should the project manager implement to deal with this situation?
Admin Staff asked 1 year ago
A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources
What strategy should the project manager implement to deal with this situation?

A. Discuss the problem with the team and decide how to do the work together.

B. Ask the team to accelerate the iterations and avoid interruptions.

C. Recommend that the project sponsor increases the budget to bring new resources.

D. Verify team performance and ask for improvement during daily standup meetings.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.