A project manager has recently been asked to take over an existing project that is halfway through execution. The project sponsor asked the project manager to ensure that the work carried out and the product being created do not deviate from the prescribed business value. What should the project manager do to achieve this goal?

QuestionsCategory: PMPA project manager has recently been asked to take over an existing project that is halfway through execution. The project sponsor asked the project manager to ensure that the work carried out and the product being created do not deviate from the prescribed business value. What should the project manager do to achieve this goal?
Admin Staff asked 1 year ago
A project manager has recently been asked to take over an existing project that is halfway through execution. The project sponsor asked the project manager to ensure that the work carried out and the product being created do not deviate from the prescribed business value.
What should the project manager do to achieve this goal?

A. Review the requirements management plan.

B. Monitor the work breakdown structure (WBS).

C. Carry out quality audits and failure analyses.

D. Review the benefits realization plan.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.