A project manager has recently been asked to take over an existing project. The project manager would like to determine how the project has been progressing by tracking features that are in progress. completed. or scheduled to be worked on. Which of the following can help the project manager assess the state of the project? A. Cumulative flow diagram B. Burndown chart C. Pareto diagram D. Burnup chart Correct Answer: A This question is in PMP exam For getting PMP Certificate