A project manager has recently been assigned to a new project. When the project manager first meets the project team, the team tells the project manager that all of the management plans and documents for the project are missing. What should the project manager do?

QuestionsCategory: PMPA project manager has recently been assigned to a new project. When the project manager first meets the project team, the team tells the project manager that all of the management plans and documents for the project are missing. What should the project manager do?
Admin Staff asked 1 year ago
A project manager has recently been assigned to a new project. When the project manager first meets the project team, the team tells the project manager that all of the management plans and documents for the project are missing.
What should the project manager do?

A. Continue working on scheduled tasks to avoid delaying the project and leave the development of project artifacts for later.

B. Ask the stakeholders to develop all of the project artifacts so the project team can continue their scheduled activities.

C. Adapt the project management plans and documents from previous executed projects in order to save time.

D. Create the project management plans with the project team and share the documents with the stakeholders.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.