A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?

QuestionsCategory: PMPA project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?
Admin Staff asked 1 year ago
A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?

A. Ask the project sponsor to replace the contractor since they do not have agile experience

B. Issue a formal notice to the contractor to obtain an agile certi cation.

C. Instruct the contractor to receive agile training since the project has already started.

D. Consult the project team to understand the extent of the training needs for the contractor.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.