A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do? A. Ask the project sponsor to replace the contractor since they do not have agile experience B. Issue a formal notice to the contractor to obtain an agile certi cation. C. Instruct the contractor to receive agile training since the project has already started. D. Consult the project team to understand the extent of the training needs for the contractor. Correct Answer: D This question is in PMP exam For getting PMP Certificate