A project manager held a meeting and framed the project schedule. A critical stakeholder, who was not consulted at the time of the schedule discussion, complained that the published dates are not agreeable due to a prescheduled task for another assignment. What should the project manager do first? A. Organize a new schedule framing meeting with the critical stakeholder to obtain input. B. Discuss with the project sponsor and create a new project schedule. C. Analyze the root cause of the issue and update the communications management plan. D. Reach out to the project sponsor and request additional resources. Correct Answer: C This question is in PMP exam For getting PMP Certificate
Please login or Register to submit your answer