A project manager identifies an issue between two team members that is affecting the development of one of the deliverables during the second iteration of a project. How should the project manager address this issue to avoid any impact to the project? A. Send a warning to both team members indicating that if the issue continues, both will be removed from the project B. Escalate both team members to their respective functional managers and let them take the appropriate actions C. Contact the functional managers to request substitutes for the con icting team members D. Schedule a meeting with both team members to understand the issue and facilitate a solution that satis es both parties D Correct Answer: D This question is in PMP exam For getting PMP Certificate