A project manager is assigned to a critical project to build a complex application for a client whose goal is to achieve an ideal state for their business model, but is unsure about how to achieve the solution. What collaboration model should the project manager recommend in this situation? A. Ask the client to specify their business needs in a contract format and approve it. B. Schedule quarterly review meetings with the client. C. Request that proper stakeholders, including the client, are assigned. D. Ask the project team to write the business requirements based on the client's needs. Correct Answer: C This question is in PMP exam For getting PMP Certificate
Please login or Register to submit your answer