A project manager is assigned to a major construction project. The project is critical to the city’s population, and especially to the local government o cial who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include aspects that the previous project sponsor did not support. What should the project manager do next?

QuestionsCategory: PMPA project manager is assigned to a major construction project. The project is critical to the city’s population, and especially to the local government o cial who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include aspects that the previous project sponsor did not support. What should the project manager do next?
Admin Staff asked 1 year ago
A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government o cial who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include aspects that the previous project sponsor did not support.
What should the project manager do next?

A. Meet with the new project sponsor to review the current project scope and the requested changes.

B. Rebaseline the project as there is now a new project sponsor, which is presenting an opportunity to review and recalibrate the project objectives.

C. Invite the project sponsor to a brie ng with the project team to demonstrate progress and seek further support to meet project-committed deliverables.

D. Inform the new project sponsor that the new aspects will not be included in this project.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.