A project manager is assigned to a project. There was a lot of con ict regarding the status of the project and compliance with international regulations. During a regular meeting, the sponsor wanted to know how frequently the risks are being reviewed. Which document project manager should check first? A. Risk management plan B. Risk register C. Issue log D. Risk report Correct Answer: A This question is in PMP exam For getting PMP Certificate