A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program. How should the project manager prepare for the next steps of the project?

QuestionsCategory: PMPA project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program. How should the project manager prepare for the next steps of the project?
Admin Staff asked 1 year ago
A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.
How should the project manager prepare for the next steps of the project?

A. Escalate to the management team to increase the timeline based on the complexity of the project

B. Wait for the other project estimates before planning the schedule

C. Prioritize and estimate the milestones for the high-level requirements based on historical data

D. Ask the project management office (PMO) to estimate the tasks for all the projects and share the project management plan










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.