A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager’s peers informs the project manager that a project with the same scope for a different country was completed 1 year ago. What should the project manager do first?

QuestionsCategory: PMPA project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager’s peers informs the project manager that a project with the same scope for a different country was completed 1 year ago. What should the project manager do first?
Admin Staff asked 1 year ago
A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago.
What should the project manager do first?

A. Register a new risk in the risk management plan.

B. Review organizational process assets (OPAs) and perform analogous estimating.

C. Ask for additional resources and review the project estimate.

D. Complete a bottom-up estimation for the project activities.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.