A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed. What should the project manager do? A. Work on the backlog activities with fewer story points. B. Ask for more resources to clear the backlog activities. C. Prioritize which backlog activities should be kept. D. Assign an owner for each backlog activity and track progress Correct Answer: C This question is in PMP exam For getting PMP Certificate