A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed. What should the project manager do?

QuestionsCategory: PMPA project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed. What should the project manager do?
Admin Staff asked 1 year ago
A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?

A. Work on the backlog activities with fewer story points.

B. Ask for more resources to clear the backlog activities.

C. Prioritize which backlog activities should be kept.

D. Assign an owner for each backlog activity and track progress










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.