A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6 months. What should the project manager do to align stakeholders' needs and expectations? A. Work with the stakeholders to create a prioritized backlog and release a roadmap. B. Modify the requirements to those that can be completed in 6 months. C. Implement fast-tracking and crashing activities to complete the project in 6 months. D. Include all stakeholders in daily scrum meetings to keep them informed. Correct Answer: A This question is in PMP exam For getting PMP Certificate