A project manager is in a team meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change. What should the project manager do? A. Follow the stakeholder engagement plan. B. Review the stakeholder map along with the organizational chart and delegate the most senior person to make the decision. C. Schedule a project decision meeting with all stakeholders to discuss the decision. D. Make the decision on behalf of the organization. Correct Answer: A This question is in PMP exam For getting PMP Certificate