A project manager is initiating a project to create a new service that has never been done before in their organization. The project manager is trying to determine what resources are required for their project team but is receiving con icting resource requirements from the team, sponsor, and key stakeholders. What should the project manager do next? A. Identify the resources that are agreed upon to initiate the project and request additional resources later. B. Determine if there is a subject matter expert (SME) who has expertise in the new service to assist with resource requirements. C. Evaluate and prioritize the resource requests from the project's key stakeholders. D. Evaluate the resource options and propose alternatives to the project team for their approval. Correct Answer: D This question is in PMP exam For getting PMP Certificate