A project manager is initiating a project to create a new service that has never been done before in their organization. The project manager is trying to determine what resources are required for their project team but is receiving con icting resource requirements from the team, sponsor, and key stakeholders. What should the project manager do next?

QuestionsCategory: PMPA project manager is initiating a project to create a new service that has never been done before in their organization. The project manager is trying to determine what resources are required for their project team but is receiving con icting resource requirements from the team, sponsor, and key stakeholders. What should the project manager do next?
Admin Staff asked 1 year ago
A project manager is initiating a project to create a new service that has never been done before in their organization. The project manager is trying to determine what resources are required for their project team but is receiving con icting resource requirements from the team, sponsor, and key stakeholders.
What should the project manager do next?

A. Identify the resources that are agreed upon to initiate the project and request additional resources later.

B. Determine if there is a subject matter expert (SME) who has expertise in the new service to assist with resource requirements.

C. Evaluate and prioritize the resource requests from the project's key stakeholders.

D. Evaluate the resource options and propose alternatives to the project team for their approval.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.